The Atwood Village Board president and trustees have a 3-year plan they are working on for the village. This article will give you plans for FY 2022-2023 & 2023-24 for some of the departments. Approximately every couple of weeks, we will bring you additional departments with their projects.
WATER & SEWER DEPARTMENT: 2022-2023
Install remaining high service pump at sewer plant. (Done)
Clean/seal coat water tower (Done)
Continue mapping service-water/sewer (Done)
New blowers/bar screens at sewer plant (Waiting on bid)
Purchase 1-ton dump truck w/blade, share cost with streets (move to 2023/24)
Replace end points on water meters (done)
Purchase attachments for Hydro-vac/Jetter (move to 2023-24)
WATER & SEWER DEPARTMENT: 2023-2024
Remodel sewer plant building (move to 2024-2025)
Replace sewer generator
New blowers/bar screens
PARKS & RECREATION: 2022-2023
Parking for SE & T-ball diamonds (Done)
Purchase additional land west of park (in process)
Paint exterior concession, gates, sign posts, benches, etc. (Done)
Repair concession door & replace A/C
PARKS & RECREATION: 2023-2024
Oil/chip roads
Lighting on SE diamond & upgrade to LED
Install more LED lights on NW Diamond
More red field product
STREETS & ALLEYS: 2022-2023
Business District resurfacing & refinancing of current loan
Sidewalk Replacements
Storm sewer repairs/cleanouts
Tree install/trimming & removals (Done)
Street drainage issues (Main St., Indiana St. W. Central, N. Juniper Dr.)
Business district beautification plan (in progress)
1-ton dump truck w/blade (shared cost with w/s) (move to 2023-23)
Horse shelter
STREETS & ALLEYS: 2023-2024:
Business District beautification plan (in progress)
Sidewalk replacements or installs
Storm sewer repairs/cleanout
Tree install/trimming & removals
Street drainage issues (Main St., Indiana St., West Central & N. Juniper Drive)
Business district beautification plan (in progress)
John Deere mower replacement